Madurai - Manamadurai - Rameswaram Electrification

 
 Topic Tags 
There are no Forum Tags

Post new topic   Reply to topic    IR Southern Zone - Discussion Forum Index -> -> Project Updates
View previous topic :: View next topic  
Author Message
rojaraju



Joined: 30 May 2013

Posts: 926
Location: SVKS Sivakasi/ NDLS New Delhi

PostPosted: Thu Sep 13, 2018 10:37 am    Post subject: Madurai - Manamadurai - Rameswaram Electrification If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

--------------------
13-th=sep/2018
--------------------

Madurai - Manamadurai - Rameswaram Electrification

--------------------------------------------------------------------------
Railways agrees for electrification in Madurai-Rameswaram sector: MP
---------------------------------------------------------------------------

THE HINDU
SEPTEMBER 12, 2018 19:20 IST
Ramanathapuram

Southern Railway has agreed for electrification in the Madurai–Rameswaram sector and introduce two new trains — bi-weekly express between Ernakulam and Rameswaram and bi-weekly express between Mangalore junction and Rameswaram, local MP A. Anwhar Raajhaa has said.

Giving details of the deliberations at the meeting of the Members of Parliament of the region served by Madurai division, chaired by Southern Railway General Manager R.K. Kulshrestha in Madurai on Tuesday, Mr. Raajhaa said the electrification would help to enhance train services.

He said the railway board had sanctioned the electrification and sanctioned a sum of ₹185.37 crore. The work would commence immediately, he said. On introduction of DEMU services, the officials said that there were no maintenance facilities for DEMU rakes either at Madurai or at Rameswaram and it was operationally not feasible.

He, however, pitched hard for the service, stating if the Southern Railway could operate DEMU services in the Virudhunagar – Tiruchi and Manamadurai – Mannargudi sectors, why not in the Rameswaram – Madurai sector.

He also pressed for daytime express between Rameswaram and Chennai and naming it after former president A.P.J. Abdul Kalam but the officials said it was not feasible to run new trains in the sector for the present.

When he pressed for the re-introduction of the Rameswaram Coimbatore daily express and three pairs of Rameswaram – Palakkad passenger trains, the officials said Southern Railway proposed bi-weekly train from Mangalore junction to Rameswaram via Madurai – Dindigul, Palani – Pollachi – Podanur – Palakkad.

It also proposed a new bi-weekly train between Ernakulam and Rameswaram via Madurai – Dindigul – Palani – Pollachi – Palakkad. Railway board’s orders were awaited for the two trains, he said quoting the officials.

The MP said the officials had agreed to provide stoppages for the two express trains between Rameswaram and Chennai at Uchipuli after upgrading the platform. They had also agreed to enhance passenger amenities in Paramakudi, Ramanathapuram and Rameswaram railway stations, he said.
---------------------------------------------------------------------------


https://www.thehindu.com/news/cities/Madurai/railways-agrees-for-electrification-in-madurai-rameswaram-sector-mp/article24935972.ece


---------------
rojaRAJU, O+
=========
Back to top
View user's profile Send private message
rojaraju



Joined: 30 May 2013

Posts: 926
Location: SVKS Sivakasi/ NDLS New Delhi

PostPosted: Thu Sep 13, 2018 11:33 am    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

--------------------
13-th=sep/2018
--------------------

Happy to see new Madurai - Rameswaram Electrification project announcement with mention about works would start immediately ...

It is obvious that WITHOUT POLITICAL INTERVENTION Rlys does amazing works, what is REQUIRED/ what is NECESSARY ... To point out, this MDU RMM electrification project has not been 'demanded' or 'highlighted' by any association/ MP or the like ...

Being Electrification promoted, Electrification Surveys for ALL current non-electric tracks in Tamil Nadu have been called on this jan 2018... All these surveys would have been completed by now...

While SA division is taking ED - KRR - TPJ, SA - KRR - DG electrification, TPJ division is undertaking TPJ - KIK/ VLNK electrification, according to me, MDU division would have taken this MDU - RMM electrification one as priority ...

I thought, MDU division would take electrification of TEN - TCN and DG - POY - PGT first and then VPT - SCT ... As GOC having shed of diesel locos, I thought MDU / TPJ - MNM - RMM would be the last section to be electrified ...

In this MDU - RMM electrification, my question is how would they go for wiring in Pamban bridge... As wiring is not possible in NEW SINGLE truss span up down moving bridge being constructed/ planned replacing old Scherzer's span bridge...

Of course, services will be increased as RMM needs more connection with places out of Tamil Nadu too because of its pilgrimage centre status and new APJ Abdul Kalam memorial and tourist island status ...

And electrification would ensure seamless operation by elocos ...

My proposition would be to electrify from MDU till MMM Mandapam and leave MMM Mandapam - RMM Rameswaram as it is ...





---------------------------------------------------------------------------
[/color][/i]

https://timesofindia.indiatimes.com/city/chennai/after-century-span-pamban-bridge-will-rise-as-one-to-let-ships-through/articleshow/62667726.cms


---------------
rojaRAJU, O+
=========
Back to top
View user's profile Send private message
srirangam99



Joined: 17 Nov 2007
Age: 55

Posts: 4495


PostPosted: Thu Sep 13, 2018 9:33 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

Hi Rajadurai,

is TPJ-KKDI-MNM electrification also an approved project?
_________________
N.Srinivasan
New Delhi
Back to top
View user's profile Send private message
mahavmsrt



Joined: 23 Jul 2011
Age: 37

Posts: 2465
Location: Sivakasi/Chennai

PostPosted: Thu Sep 13, 2018 10:57 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

Cheenu,
srirangam99 wrote:
Hi Rajadurai,

is TPJ-KKDI-MNM electrification also an approved project?

All over India all BG lines approved for electrification..

You can see the topic for TPJ KKDI MNM VPT SCT section electrification in project updates..
_________________
Cheers,
Mahendran
Back to top
View user's profile Send private message Send e-mail
srirangam99



Joined: 17 Nov 2007
Age: 55

Posts: 4495


PostPosted: Fri Sep 14, 2018 9:06 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

No Mahe, I meant if TPJ-MNM VIA PDKT-KKDI has been approved in any previous Railway Budget.
_________________
N.Srinivasan
New Delhi
Back to top
View user's profile Send private message
mahavmsrt



Joined: 23 Jul 2011
Age: 37

Posts: 2465
Location: Sivakasi/Chennai

PostPosted: Fri Sep 14, 2018 10:46 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

srirangam99 wrote:
No Mahe, I meant if TPJ-MNM VIA PDKT-KKDI has been approved in any previous Railway Budget.

No..Previous budgets didn't approved for TPJ MNM electrification..
_________________
Cheers,
Mahendran
Back to top
View user's profile Send private message Send e-mail
srirangam99



Joined: 17 Nov 2007
Age: 55

Posts: 4495


PostPosted: Sat Sep 15, 2018 12:42 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

mahavmsrt wrote:
No..Previous budgets didn't approved for TPJ MNM electrification..


well obviously SR erred. When they have approval of VM-TPJ via MV-KMU-TJ, then obviously they should have proposed electrification of TPJ-MNM-RMM also so that the Boat Mail route got electrified.

_________________
N.Srinivasan
New Delhi
Back to top
View user's profile Send private message
Pbv15124



Joined: 06 Jun 2017
Age: 41

Posts: 390
Location: chennai

PostPosted: Sat Sep 15, 2018 3:19 pm    Post subject: If a post contains some illegal issues you may abuse on it - just click Abuse and fill the form Reply with quote

From operation point of view access to GOC diesel shed/Workshop is very important for SR until 100% section gets electrified. So TPJ-KKDI-MNM section might be taken up after electrification of VM-MV-TPJ, TJ-KIK, MV-TVR.
MDU-MNM-RMM has no such issues SR electrify this section before taking up TPJ-MNM and TVR-KKDI section.
_________________
Regards
Suganthan
Back to top
View user's profile Send private message
Display posts from previous:   
Post new topic   Reply to topic    IR Southern Zone - Discussion Forum Index -> -> Project Updates
All times are GMT + 5.5 Hours
Page 1 of 1

 
Jump to:  
You cannot post new topics in this forum
You cannot reply to topics in this forum
You cannot edit your posts in this forum
You cannot delete your posts in this forum
You cannot vote in polls in this forum


© 2007 Informe.com. Get Your Own Free Portal.
Powered by phpBB © 2001 - 2005 phpBB Group
Theme ACID v. 2.0.18 par HEDONISM